The change of the plan for the centennial flood control project in qinhuangdao
Release time:2019-01-24
The east - west extension project of haibin road has been widely concerned by the citizens of qinhuangdao.
The project was partially modified. The municipal bureau of administrative examination and approval issued the reply as follows:
I. the construction nature of the east-west extension project of haibin road is divided into two parts, one is the new construction project, the other is the maintenance project. Management within the scope of the project channel construction project engineering construction scheme has been our bureau approval, the project will change the original plan of the "seaside Lucy delay travelling across the large and small tanghe respectively" instead of "seaside Lucy delay so integral drawing water across the large and small and the channel island", were set up stream crossing three: coastal Lucy delay across the size of the main river crossing soup (a), seaside Lucy river crossing delay travelling across size soup (two). The cross-section of the cross-river bridge is consistent with the original plan. The length of the main road across the size of the tanghe bridge (one) is 562m. The auxiliary road spans the size of tanghe bridge (two Bridges) and is arranged in two sections, with the length of 506.371m in the north and 492.986m in the south. The auxiliary Bridges in both north and south are arranged in 5 sections.
Agree that the proposed bridge design flood control standard for this project shall be once in 100 years.
Iii. In the proposed bridge, the main bridge and the existing river bank are designed as overpass, and the auxiliary bridge and the existing river bank are designed as flat intersection. Plans to build a bridge with large tanghe river crossing Angle is 80 °, with small tanghe river crossing Angle is 70 °, meet the flood control evaluation river management within the scope of construction projects in hebei province technical review regulations (try out) ". Under the current situation and planning conditions, the minimum design beam bottom elevation of the proposed bridge in tanghe is higher than the calculated minimum allowable height at the bottom of the bridge beam once every 100 years.
4. The top elevation of bridge pier cap in the proposed bridge channel does not meet the requirement that "the top elevation of bridge pile foundation cap (tie beam) should be less than 0.5m below the scouring line" in flood control evaluation technical review regulations for construction projects within the river management scope of hebei province (trial) ". The construction unit shall take measures according to the requirements of flood control evaluation report.
5. As the proposed bridge construction may affect a third party, coordination shall be made with relevant departments before the commencement of the project.
6. Construction is prohibited during the flood season, and construction facilities in the river should be cleared before the flood season to ensure the smooth flow of flood, and construction garbage in the river should be cleared after the completion of the project to restore the original appearance of the river and ensure the safety of flood discharge.
Project construction and construction shall be carried out in strict accordance with the requirements of flood control evaluation report, and the approved scheme shall not be changed at will without approval.
Viii. The project shall be supervised by the water conservancy administrative department. The construction unit shall go through relevant procedures with the relevant department before commencement of construction, and the construction period and operation period shall be subject to the relevant provisions and management of the water conservancy administrative department. Upon completion and acceptance of the proposed project facilities, the water conservancy administrative department shall participate.